Title: E4tech (2012) BVCM Biomass conversion 2nd generation energy crops to gas BioSNG large 2050 2050 Content: Change over time based on CT TINA bioenergy. Plant costs given are for a fully commercial plant in 2020, hence costs in 2010 are based on a pioneer plant (2.1 times as expensive) User: Richard Taylor Signed off by: Signed off at: Cost category: Biomass conversion 2nd generation energy crops to gas cost data Cost source: E4tech (2012) BVCM cost source Valid for quantity of fuel: Valid in year: 2050 Efficiency: 70% Life: 20 years Size: 200MW Fuel: Operating: £(2010) 0.018-0.031m/MW Capital: £(2010) 0.38-0.68m/MW Default fuel unit: Default operating unit: £(2000)/GJ Default capital unit: £(2000)/GJ Label: BioSNG large 2050 Output: 80% |