Coal CCS cost data

Return to the cost category.

Showing just the changes made in the edit by Joseph Downie at 2011-11-29 10:07:00 UTC

See all changes since this wiki was released

2011-11-29

2011-08-10

Title: Coal CCS cost data

Content: CAPEX is the overnight cost of building a power plant per KW (Gross, i.e. before parasitic load and load factor)

Includes all kinds of solid fuel electricity generation with carbon capture and storage: pre and post combustion; coal and biomass fuelled.

Excludes the cost of fuel. See: 

# Summary of coal cost data points
# Summary of imported biomass cost data points

Includes the cost of carbon capture, but not transport and storage. See:

# Summary of carbon transport cost data points
# Summary of carbon storage cost data points

Category: CCS Costs



User: Michael Clark

Signed off by: 

Signed off at: 

Default fuel unit: 

Default operating unit: £(2010)/kwpeak

Default capital unit: £(2010)/kwpeak

Label: Coal CCS
Title: Coal CCS cost data

Content: CAPEX is the overnight cost of building a power plant per KW (Gross, i.e. before parasitic load and load factor. Cost sources originally in Net form have been converted to Gross.)   

Includes all kinds of solid fuel electricity generation with carbon capture and storage: pre and post combustion; coal and biomass fuelled.

Excludes the cost of fuel. See: 

# Summary of coal cost data points
# Summary of imported biomass cost data points

Includes the cost of carbon capture, but not transport and storage. See:

# Summary of carbon transport cost data points
# Summary of carbon storage cost data points

Category: CCS Costs



User: Joseph Downie

Signed off by: 

Signed off at: 

Default fuel unit: 

Default operating unit: £(2010)/kwpeak

Default capital unit: £(2010)/kwpeak

Label: Coal CCS