MARKAL 3.26 Hydroelectricity Default - Hydro power - Large (>20 MW) 2010

Return to the cost.

Showing all changes since you last edited this page on 2011-10-24 17:07:02 UTC

See all changes since this wiki was released

2011-11-28

2011-10-24

Title: MARKAL 3.26 Hydroelectricity Hydro power - Large (>20 MW) 2010

Content: h2 Items that this cost includes

h2 Items that this cost excludes

h2 Detail on the conditions under which this cost is valid

h2 Explanations as to why this cost differs from others

h2 Limitations of this cost estimate

Categories:
Cost data points
Hydroelectricity cost data points



User: 

Signed off by: 

Signed off at: 

Cost category: Hydroelectricity cost data

Cost source: MARKAL 3.26 cost source

Valid for quantity of fuel: 

Valid in year: 2010

Efficiency: 

Life: 

Size: 

Fuel: 

Operating: £(2000) 80 / kw

Capital: £(2000) 800 / kw

Default fuel unit: 

Default operating unit: £(2010)/kWpeak

Default capital unit: £(2010)/kWpeak

Label: Hydro power - Large (>20 MW)

Output:
Title: MARKAL 3.26 Hydroelectricity Default - Hydro power - Large (>20 MW) 2010

Content: h2 Items that this cost includes

h2 Items that this cost excludes

h2 Detail on the conditions under which this cost is valid

h2 Explanations as to why this cost differs from others

h2 Limitations of this cost estimate

Categories:
Cost data points
Hydroelectricity cost data points



User: Tom Counsell

Signed off by: 

Signed off at: 

Cost category: Hydroelectricity cost data

Cost source: MARKAL 3.26 cost source

Valid for quantity of fuel: 

Valid in year: 2010

Efficiency: 

Life: 

Size: 

Fuel: 

Operating: £(2000) 80 / kw

Capital: £(2000) 800 / kw

Default fuel unit: 

Default operating unit: £(2010)/kWpeak

Default capital unit: £(2010)/kWpeak

Label: Default - Hydro power - Large (>20 MW)

Output: