II.a Nuclear power costs

Return to the page.

Showing all changes since 2011-04-27 17:24:58 UTC

See all changes since this wiki was released

2011-11-09

2011-10-05

2011-10-03

2011-09-13

2011-09-11

2011-09-09

2011-08-28

2011-08-23

2011-04-27

Title: 2050 Nuclear power costs

Content: h1 Lead and sign-off

2050 Costs team lead - Michael Clark 

Working-level analyst - Henry Shennan, Anthony Moulds (DECC)

Senior analyst - Sam Thomas

h1 Data sources

MottMac10

Markal3.24Doc

MottMac11

ESME

Summary: D11/859001 Excel sheet: D11/729334

h1 Technologies costed in this sector

* Nuclear power plant
* Uranium enrichment
* Uranium imports
* Uranium disposal

h1 Nuclear power plant

Costs summary (£ per KW):

| Overall   | Low  | High   |
| Capital   | 1702 | 4418.8 |
| Operating | 46   | 97     |

h2 Current Calculator assumptions

* Lifetime =  No retirement before 2050 for new build from 2020, current legacy retires by 2035
* Efficiency =  36% thermal efficiency, 10% own use as a percentage of supplied electricity
* Load factor = 60-80% 
* Input Fuel = Uranium

h2 Investment Cost sources

* High cost = Nuclear 3rd Generation PWR - FOAK, from MottMac10, Availability = 100%, Aux power = 5.5% Life = 60yrs
* Low cost = Nuclear plant, - 30% from ref from ESME, Electrical efficiency = 38-41%, Availability = 85%, Life = 50yrs

h2 Fixed Operating Cost sources

* High cost = Nuclear 3rd Generation PWR - FOAK, from MottMac10, Availability = 100%, Aux power = 5.5% Life = 60yrs
* Low cost = Nuclear 3rd Generation PWR - NOAK, from MottMac10, Aux power = 4%, Availability = 80%, Life = 60yrs

h2 Built plant estimates

The headline figure often talked about by the leading UK developers (EdF and Horizon) and the UK government is £10bn for a twin or triple unit plant with a capacity of about 3GW net.  This is equivalent to about £3300/kW (€3800/kW and $4900/kW). UAE’s price for Kepco’s APR concluded in late 2009 (about £2400 (~$3,600).[MottMac11]

Both of these real world estimates fall within the range above.

h1 Uranium enrichment

Markal High cost of processing was 19% uranium enrichment and fuel fabrication and low cost 4.5%. 

h1 Uranium Imports

Uranium price assumptions taken from Markal3.24Doc Chapter 3 page 15.

Low costs = Global average lower range cost $30/kg, original source OECD/IAEA 2002 Assume global resources are 0.8Mt

High costs = Global average undiscovered uranium cost of $240/kg (note upper cost range of known resources is $110/kg), assume global resource is over 6.8Mt

h1 Uranium disposal

Markal - a constant price of £0.38m/PJ

h1 Issues, concerns and questions

* The cost of uranium disposal only occurs within the time period 2007-2050 and the cost of storage in those years beyond 2050 isn't accounted for.

Category: 2050 pathway costs



User: Tom Counsell

Picture updated at: 

Signed off by: 

Signed off at:
Title: II.a Nuclear power costs

Content: The cost of building and running a nuclear power station complex, including:

* Nuclear Power cost data
* Uranium Enrichment & Disposal cost data
* Imported Uranium cost data

Decomissioning plant costs are assumed to be captured as a surcharge on the cost of uranium enrichment and disposal costs. Please see annex E for the estimated reactor decommissioning costs in DECC's recent consultation [http://www.decc.gov.uk/assets/decc/consultations/nuclearfixedunitprice/1_20100324145948_e_@@_consultationonfixedunitpricemethodologyandupdatedcostestimates.pdf]

h1 Costs Methodology

h2 Methodology used

The user defines the number of nuclear power plants. Once the trajectory is set by the user, the number of plants to be built are defined. Investment costs are a function of new build and operating cost are a function of the number of plants operating within that time period.

Please see 2050 Methodology for a full description of the costs approach in the Calculator.

h2 Methodology issues and uncertainty

* We assume the current nuclear fleet retires by 2035 but we do not include the possibility of extending the lifetimes of the plants. Could the plants realistically have their lifetimes extended and what will this cost?

* Should we split out further the costs of uranium enrichment, waste and plant decommissioning?

h1 Technical Assumptions

* Lifetime =  60 years therefore no new build retirement before 2050 for new build from 2020, current legacy retires by 2035
* Efficiency =  36% thermal efficiency, 10% own use as a percentage of supplied electricity therefore 32.7% efficiency from uranium in to electricity supplied to the grid
* Load factor = 60% today, raising to 80% by 2050, then remaining constant.
* Input Fuel = Uranium

h1 Questions to Stakeholders

* The cost of uranium disposal only occurs within the time period 2007-2050 and the cost of storage in those years beyond 2050 isn't accounted for. Should we include this residual cost or is it immaterial and/or captured within the waste cost as a function of uranium used?

* Should we include decommissioning costs or are they captured within waste costs?  Check with Richard Marriott in OND. Proven numbers are about US$500million for a 1GW PWR (a real US example) which when expressed as £/MWh is a small number. 

h2 Built plant estimates

The headline figure often talked about by the leading UK developers (EdF and Horizon) and the UK government is £10bn for a twin or triple unit plant with a capacity of about 3GW net.  This is equivalent to about £3300/kW (€3800/kW and $4900/kW). UAE’s price for Kepco’s APR concluded in late 2009 (about £2400 (~$3,600).[MottMac11]

Both of these real world estimates fall within the range above.

h1 General comments

Please use this space to make any general comments.  Please add your name when commenting.

Note from Tim Stone - the 60-80% load factors are out of date.  Exelon run above 90% with good management of older plants and the new ones should achieve this sort of number far more easily by design - better with really good management.    Needs updating.

Response from Tom Counsell - I've corrected the wording to be clear that we are assuming that 60% is the historic load factor, and that 80% is the load factor assumed for the future. When we update the assumptions we are going to have to think carefully about load factors for all technologies: while it is demonstrably true that plants can maintain an availability of above 90%, if these technologies contribute large fractions of the energy mix and improvements in storage are not forthcoming then they will need to load follow and will not be able to have such high load factors. 

Response from Mike Knowles MIMechE - As a co-author of the Institution of Mechanical Engineers' energy policy statement EP11/02 on "UK Electricity Generation - Cost effective management"http://www.imeche.org/Libraries/Position_Statements-Energy/UK_Electricity_Generation.sflb.ashx, it is very important that right from the start that 3rd generation Areva EPRs and Westinghouse AP1000 new nuclear plant should have high 80%+ load factors. To give best value for money for end users,they and CCS coal and gas should, as far as possible,be allowed to load follow as intermittent sources come in randomly.  

AGRs in the 1990s and early 2000s achieved quite high LFs except for unplanned outages for CO2 circulator failures on Torness. DUKES 2010 Table 5.10 gves LFs even in 2005 72.4%; 2006 69.3%;2007 59.6% and 2008 49.4% and 2009 back to 65.4% in 2009. Average over the five years is 63.4%.  

Examples of current practice with PWR plant is very good.  

3rd Generation Areva EPRs and Westinghouse AP1000 designs are built with safety and redundancies to the fore. There should be a presumption that new UK nuclear plants will start with load factors nearer to 80%.  EdF has 90%  nuclear plant (capacity 63GWe). They do load follow--some even close at weekends. Their capacity factor of 77.3% is low by world standards but availibility is increasing and is now 84%. We should certainly assume 80% for new 3rd Generation UK plant. 

Sizewell B's first 15 years of commercial operation with accounting closure at 2035 is shown at  http://www.iaea.org/cgi-bin/db.page.pl/pris.ophis.htm?country=GB&site=SIZEWELL%20B&refno=24&opyear=2020, .  This shows that since the commencement of operation in 1995 Sizewell B Westinghouse PWR nuclear plan has a cumulative availability factor up to 2010 of 83.47%! 

The government itelf revealed that the 1,600 MW projected units, to be called Sizewell C, would, together with the planned units at Hinkley Point, contribute 13% of UK electricity in the early 2020s.[1] EDF plans to use Areva's EPR design for any new build reactors in the UK; the design of reactors currently being built in Finland and France.[1] ref Wikipedia. 

+