The UK 2050 Calculator Web Flash Excel Wiki
Register or sign in
This is a wiki Anyone can contribute, therefore we don't vouch for its accuracy.

MARKAL 3.26 Nuclear Power Default - Nuclear Power - PWR - Existing 2010

Return to the cost.

Showing just the changes made in the edit by at 2011-10-24 16:38:59 UTC

See all changes since this wiki was released

2011-11-28

2011-10-24


Title: MARKAL 3.26 Nuclear Power Nuclear Power - PWR - Existing 2010

Content: Please explain how the following costs have been treated:

# Uranium extraction and processing
# Uranium storage
# Uranium disposal
# Connection costs to national grid

You may also wish to comment on:

# Items that this cost excludes or includes
# The conditions under which this cost is valid
# Why this cost differs from others
# Any limitations of this cost estimate

Categories:
Cost data points
Nuclear Power cost data points



User: 

Signed off by: 

Signed off at: 

Cost category: Nuclear Power cost data

Cost source: MARKAL 3.26 cost source

Valid for quantity of fuel: 

Valid in year: 2010

Efficiency: 

Life: 

Size: 

Fuel: 

Operating: £(2000) 42.8/ kw

Capital: £(2000) 1913/ kw

Default fuel unit: 

Default operating unit: £(2010)/kw

Default capital unit: £(2010)/kw

Label: Nuclear Power - PWR - Existing

Output: