CEPA et al 2010 Electricity Transmission MEAV

Return to the cost.

Showing just the changes made in the edit by Tom Counsell at 2011-07-06 11:22:40 UTC

See all changes since this wiki was released

2011-07-06


Title: CEPA et al 2010 Electricity Transmission MEAV

Content: Source gives a total Modern Equivalent Asset Value (MEAV) for the GB transmission grid, but not an operating cost. I have divided this total cost by 77 GW to match the way it would be used in the 2050 pathways calculator.

I understand MEAV to mean the cost of replacing the whole grid tomorrow. This is higher than the regulated asset value, which appears to be based on historic cost.



User: Tom Counsell

Signed off by: 

Signed off at: 

Cost category: Electricity Transmission cost data

Cost source: CEPA et al 2010 cost source

Valid for quantity of fuel: 

Valid in year: 

Efficiency: 

Life: 

Size: 

Fuel: 

Operating: 0

Capital: £(2010)37bn/77GW

Default fuel unit: 

Default operating unit: 

Default capital unit: 

Label: MEAV