Renewable UK Marine Report 2010 Wave First Wave Farm 2010

Return to the cost.

Showing just the changes made in the edit by Tom Counsell at 2011-06-29 15:15:28 UTC

See all changes since this wiki was released

2011-06-29


Title: Renewable UK Marine Report 2010 Wave First Wave Farm 2010 cost data point

Content: Cost is given for TRL8-9 2-10 MW wave farms (i.e., pre commercial). States that there is the potential for 15% learning rate subsequently.

Categories:
Cost data points
Wave cost data points



User: Tom Counsell

Signed off by: 

Signed off at: 

Cost category: Wave cost data

Cost source: Renewable UK Marine Report 2010 cost source

Valid for quantity of fuel: 

Valid in year: 2010

Efficiency: 

Life: 25 years

Size: 10 MW

Fuel: 

Operating: £m(2010)0.9-4.2/10MWpeak

Capital: £m(2010)42-82/10MWpeak

Default fuel unit: 

Default operating unit: 

Default capital unit: 

Label: First Wave Farm

Output: 30-35%