Bloomberg Nuclear Power Flamanville 3, France EPR (Under construction) 2010

Return to the cost.

Showing just the changes made in the edit by Michael Clark at 2011-06-19 11:42:40 UTC

See all changes since this wiki was released

2011-06-19


Title: Bloomberg Nuclear Power Flamanville 3, France (Under construction) 2010 cost data point

Content: Includes finance costs: Areva European Pressurized Reactor type and is planned to have a capacity of 1,650 MWe. Bloomberg cost estimate: http://www.bloomberg.com/news/2010-07-29/edf-said-to-raise-flamanville-costs-to-6-5-billion-delay-reactor-starts.html 

Technical specifications from EDF site: http://energie.edf.com/nucleaire/carte-des-centrales-nucleaires/epr-flamanville-3/la-technologie-epr-48325.html 

Operating cost unknown



User: Michael Clark

Signed off by: 

Signed off at: 

Cost category: Nuclear Power cost data

Cost source: Bloomberg cost source

Valid for quantity of fuel: 

Valid in year: 2010

Efficiency: 36%

Life: 60 years

Size: 1.6GW

Fuel: 

Operating: £(2010)0/KW

Capital: €(2010)4-5bn/1650MW

Default fuel unit: 

Default operating unit: 

Default capital unit: 

Label: Flamanville 3, France (Under construction)

Output: 96%