Markal 3.24 Hydroelectricity >20MW 2000

Return to the cost.

Showing just the changes made in the edit by Michael Clark at 2011-06-09 17:03:25 UTC

See all changes since this wiki was released

2011-06-09


Title: Markal 3.24 Hydroelectricity >20MW 2000 cost data point

Content: Enviros 2005, page 47. O&M assumed to be 10% of CAPEX



User: Michael Clark

Signed off by: 

Signed off at: 

Cost category: Hydroelectricity cost data

Cost source: Markal 3.24 cost source

Valid for quantity of fuel: 

Valid in year: 2000

Efficiency: 

Life: 40 years

Size: 

Fuel: 

Operating: £(2000)80/kwpeak

Capital: £(2000)800/KW

Default fuel unit: 

Default operating unit: 

Default capital unit: 

Label: >20MW

Output: 37%