Notes
Please comment on:
- Whether and how the costs of carbon transport and storage have been dealt with
- What assumptions are made around the energy required to run the carbon capture
Category | Temporary | |
Source | 2050 working assumption | |
Capital cost | £(2010)4323.2-821/KW | 821–4323£(2010)/KW |
Operating cost | £(2010)163-38/PJ | 0–0£(2010)/KWpeak |
Year for which cost is valid | 2050 | 2050 |
Typical size | 1.2GW | |
Typical average output | 85% | |
Typical efficiency | 32-44% | |
Typical life | 30 years |