Notes
Includes finance costs of construction project, see: http://www.businessweek.com/news/2010-06-24/areva-s-overruns-at-finnish-nuclear-plant-approach-initial-cost.html
Operating costs unknown, therefore zero
Category | Nuclear Power | |
Source | Bloomberg | |
Capital cost | €(2010)3-5.7bn/1600MW | 1631–3099£(2010)/kw |
Year for which cost is valid | 2010 | 2010 |
Typical size | 1.6GW | |
Typical average output | 100% |
Includes finance costs of construction project, see: http://www.businessweek.com/news/2010-06-24/areva-s-overruns-at-finnish-nuclear-plant-approach-initial-cost.html
Operating costs unknown, therefore zero