Notes
Technical details and OPEX unknown. Source: http://www.nationalgrid.com/uk/Interconnectors/Netherlands/
BritNed capital costs specified are appropriate however they imply full recovery of costs in Year 1.
Operating costs assuming utilisation rate of 60%. If the utilisation rate increases the operatig costs will reduce.
Operating costs are £0.238m/KWh. But this is far outside our range, which suggests there is an issue with opex definition, or an error in converting. So we have decided to decide the opex component.