Category | Biomass conversion 2nd generation energy crops to liquid | |
Source | E4tech (2012) BVCM | |
Capital cost | £(2010) 1.99-2.75m/MW | 236–327£(2010)/MWh |
Operating cost | £(2010) 0.11-0.16m/MW | 13–19£(2010)/MWh |
Year for which cost is valid | 2020 | 2020 |
Typical size | 150 MW | |
Typical average output | 96% | |
Typical efficiency | 40% | |
Typical life | 30 years |