Notes
Items that this cost includes
- How does it treat the energy requirement for the CCS (e.g., is the capacity net or gross of this figure)
Items that this cost excludes
- How does it treat CO2 transportation and storage?
Category | Gas CCS Electricity Generation | |
Source | MARKAL 3.26 | |
Capital cost | £(2000) 768.45 / kw | 995£(2010)/kWpeak |
Operating cost | £(2000) 30.21 / kw | 39£(2010)/kWpeak |
Year for which cost is valid | 2030- 2050 | 2030–2050 |