Category | Geothermal Electricity | |
Source | Arup/EY | |
Capital cost | £(2010)1957-5606/Kwpeak | 1957–5606£(2010)/kWpeak |
Operating cost | £(2010)143-257/Kwpeak | 143–257£(2010)/kWpeak |
Year for which cost is valid | 2020 | 2020 |
Typical size | 3.5-10MW | |
Typical average output | 90% | |
Typical life | 25 years |