Category | Offshore Wind | |
Source | Arup/EY | |
Capital cost | £(2010)1310-2301/Kwpeak | 1310–2301£(2010)/KWpeak |
Operating cost | £(2010)75-120/Kwpeak | 75–120£(2010)/KWpeak |
Year for which cost is valid | 2025 | 2025 |
Typical size | >100MW | |
Typical average output | 40% | |
Typical life | 25 years |