Category | Onshore Wind | |
Source | Arup/EY | |
Capital cost | £(2010)1062-1863/Kwpeak | 1062–1863£(2010)/KWpeak |
Operating cost | £(2010)36-65/Kwpeak | 36–65£(2010)/KWpeak |
Year for which cost is valid | 2020 | 2020 |
Typical size | 50KW-5MW | |
Typical average output | 25% | |
Typical life | 20-25 years |