Areva, Finnish nuclear build costs: http://www.businessweek.com/news/2010-06-24/areva-s-overruns-at-finnish-nuclear-plant-approach-initial-cost.html
Areva, Finnish nuclear build costs: http://www.businessweek.com/news/2010-06-24/areva-s-overruns-at-finnish-nuclear-plant-approach-initial-cost.html
Technologies | Fuels | |||||||||
---|---|---|---|---|---|---|---|---|---|---|
Valid in year | Capital cost | Operating cost excluding fuel | Size | Output | Efficiency | Life | Fuel cost | Fuel limit | ||
Nuclear Power Olkiluoto 3, Finland EPR (Under construction) | 2010 | €(2010)3-5.7bn/1600MW | 1.6GW | 100% | ||||||
Nuclear Power Flamanville 3, France EPR (Under construction) | 2010 | €(2010)3.3-6bn/1650MW | 1.6GW | 96% | 36% | 60 years |